Toro III plant was $90 million more expensive than projected

December 5, 2017 by Staff News Writer

In a matter of six years of construction, the investment made by the Costa Rican Electricity Institute (ICE) and the Junta Administradora de Servicios Eléctricos de Cartago (JASEC) in the Toro III hydroelectric project increased by more than $ 90 million.

Toro III is a water-driven hydroelectric power plant located in Venecia de San Carlos and built with an alliance between ICE and JASEC. It has an installed capacity of 46 megawatts (MW), generating 190 gigawatt hours (GWh) of renewable energy per year.

When the feasibility study was made in 2006, the investment amount of the project was calculated at $104.1 million. However, in 2012, when it was concluded, the figure reached $ 194.1 million. That is, 87% more than projected.

This was indicated by a report of the Comptroller General of the Republic (CGR). The analysis ensures that

the increase is explained by the payment of labor and indirect costs such as food, transportation and lodging for technical staff in the three years of construction.”

In addition, they note that there was delay in the judicial order for the possession of some lands, and extraordinary increases in the prices of steel, cement and fuel used in the construction of the plant also increase the final amount.

Another factor that altered the cost of the work was the redesign of works resulting from the earthquake due to the Vara Blanca-Ángel fault in 2009.

To date, ICE and JASEC have not settled expenses and costs incurred in the preoperative stage of the plant. For example, pre-investment studies cost more than $ 3.3 million and there were also more than 1.2 billion colones in benefits from the energy produced in tests.

crhoy.com

Related articles:

  1. Hydroelectric plant Reventazón will soon have a third turbine running
  2. Christiana Figueres was a special guest in the Reventazón Hydroelectric Plant’s inauguration
  3. Renewable energy creates nearly 10 million jobs worldwide
  4. $ 2.1 million plant keeps RECOPE in trouble
  5. Hydro plant output makes a thermal plant unnecesary
  6. Ashes in Toro Amarillo river

Filed Under: News Reports

SIGN UP FOR AMERICAN EXPATRIATE IN COSTA RICA

It's free, we respect your privacy and you can unsubscribe at any time.

Connect with Social Media

  • Email
  • Facebook
  • RSS
  • Twitter
Follow @expatcostarica

Search Articles and News Reports

Articles by Publication Date

June 2025
M T W T F S S
 1
2345678
9101112131415
16171819202122
23242526272829
30  
« Apr    

News Summary

U.S. President Orders Navy Task Force to Caribbean to Counter Venezuela Threat

Costa Rica Government Silent on Travel Ban with Just 13 Days Left

News Summary

Legislators approve moratorium for registration of shareholders

President confirms gasoline give away for ethanol pilot project

Chinese company sells low cost smart phones in Costa Rica

Search continues for small plane missing in Drake

Farmers will march to the Ministry of Agriculture

IMN warns of dangerous UV radiation this Friday

Copyright © 2010 to 2025 · Link to Legal Notices and Privacy Policy